Mosites Construction
built this large warehouse and office facility-seven acres under
roof-in eight months on a fast-track construction schedule.
Because
the facility was being constructed on the location of an old coal
mine, the construction timetable had to include extensive cut and
fill operations and mine grouting.
Construction
time was minimized by sequencing the concrete floor pours close
behind structural steel erection.
The
floor system, approximately 300,000 sq. ft. of concrete, was finished
within one month of the building superstructure completion.
The
mechanical systems employ the numerous dock door openings to facilitate
required air changes in the structure. The system produces an operating
cost savings of 1/3 to 1/5 of traditional HVAC systems.
|